Renovation of the Arkadiankatu bridge
The work on the Arkadiankatu bridge is progressing, and the next significant work phase is the demolition of the old deck.
The old deck structure will be dismantled on three nights during week 12
- 17.3. klo 20.00–18.3. klo 6.30
- 18.3. klo 20.00–19.3. klo 6.30
- 19.3. klo 20.00–20.3. klo 6.30
During the deck unloading, Baana will be closed at the bridge and traffic will be directed to a detour. The lid is dismantled by pulverization to cause as little noise as possible to the environment.
Further information:
MPV-Infrarakenne Oy
Ville Piirainen
ville.piirainen@infrarakenne.fi
City of Helsinki
Aki Lehtinen
aki.lehtinen@hel.fi